MS Project Filter, Groups, Highlights, Custom Filters : A tutorial

Filters, groups and highlight features allow you to see selective information you want to see in your project plan. Filters and groups play a key role in generating custom reports.  Highlight feature allows you to highlight a set of tasks based on a certain criteria.

Filters, highlight and group options in MS Project
The filters, highlight and group options can be found under the View Tab.

#1.  Highlight - Delayed Tasks, Milestones, Critical tasks and Others

The highlight feature allows you to highlight resources/tasks which meet a certain criteria. Like Filters and Groups MS Project has a few in-built highlight filters. 

The commonly used highlight filters are  Late Tasks,  Milestones, Critical Tasks etc. When you use a highlight filter the tasks which meet the criteria will be highlighted. The late task is my personal favorite as it quickly shows where the progress is slow. 

You can create custom highlight depending on your needs. It is very similar to creating a filter. You can also change the color which is used to highlight the tasks (instructions at the end of the article).


Please see Track and Highlight Tasks in MS Project to find out 3 options which you can use to find out delayed tasks.

Techno-Tip : The highlight feature sometimes does not work when the project plan uses colors which are different to default colors. So, if you see use a plan which uses different background or text colors for asks then you may not be able to use the highlight late tasks filter.

Highlight Filter in Action

Highlight Milestones in MS Project
Project Plan before Highlight Option is used

Highlight Milestones in MS Project
Project Plan after Highlight Option is used




#2.  Filters - In-built and Custom

MS Project Feature - Filter, Groups, Highlight
Filters allow you to filter tasks or resources based on the criteria selected. When you use filters you will see only the tasks or resources which you have filtered.

MS Project has some built-in filters which you can use straight away. Among all the filters my favorites are Late Tasks, Incomplete Tasks and Critical Tasks.

There is an auto filter option which will allow you to use basic filtering similar to MS Excel. You can clear any filters by  clicking on Clear Filter option in the drop down. You can also create custom filters to suit your requirements.
You can create a custom filter by clicking on New Filter Option. When the option is clicked a new window will open up.Please select the values as per the instructions.


MS Project Feature - Filter, Groups, Highlight
Creating Custom Filters
Techno-Tip : If you want to see a list of resources for a given team then create a filter which will have a condition which checks the value of  the Resource Group to be equal to the team name.

Techno-Tip : The custom filter/group/highlight created will be available in the respective drop downs under custom section.

#3.  Groups - In Built and Custom  

MS Project Feature - Filter, Groups, Highlight
Sample Resource Group Feature
Groups feature allows a grouped view of tasks or resources. Like Filters Groups also has some inbuilt group by options.

You can use the existing group by straight away. Some commonly used by group by clauses are - Active Vs Inactive, Complete vs Incomplete, Group by Resource etc.



Also if you click on "More Groups" in the groups menu you will be able to see a lot more options for groups.  Like filters you can create a custom group either based on tasks or resources.


MS Project Feature - Filter, Groups, Highlight
Creating a new Group By

Techno-Tips : 

  1. Please remember depending on which view you are in - resources or tasks - the options you see in the groups drop down will vary.
  2. You can change the color of the highlight option in the Format tab. 



MS Project Filter, Groups, Highlights, Custom Filters
Formatting Options




Swapnil Wale

Written by

Swapnil Wale is an IT Professional based in Sydney, Australia with over 10 years of experience in technology and project management. He is a passionate blogger and focuses on project management and BRMS articles.

 